b)
Bank’s approval Date of the procurement Plan [Original
Oct 31, 2007], Revised January 1, 2010:
c)
Date of
General Procurement Notice:
November 30, 2007
d)
Period covered
by this procurement plan:
January 2010- December 2010.
e)
Project Components:
·
Rehabilitation/Extension
of water and sanitation services facilitites in the six (6) WSPs areas (Lamu,Hola,Malindi,Kilifi,Kwale
and Taita Taveta)
·
Rehabilitation of the
Mzima water supply pipeline
·
Rehabilitation of the
Tiwi Boreholes/Likoni pipeline
·
Institutional
Strengthening
·
Expansion of water and
sanitation services to informal settlements
Mombasa WaSSIP (AFD Supported)
Supported by the French
Development Agency (AFD)
·
Rehabilitation/Extension
of water and wastewater services facilities in Mombasa Municipality
(including informal settlements))
·
Rehabilitation and
Expansion of the Marere water supply pipeline
·
Rehabilitation of the
Baricho Water Works
·
Institutional
Strengthening
GOK/AIE District
Based Projects
In the financial year 2010/11the GoK
district allocation amounted to Kshs201,000,000. (Two Hundred and One
Million Only). This was to be
used for the development and rehabilitation of water and sanitation
infrastructure. Currently
construction is ongoing at the District level as per the following table:
|
S/N
|
District
|
Project Name
|
Constituency
|
Budget Allocation
|
|
1
|
Likoni
|
Kiteje- Mtongwe
|
Likoni
|
13,500,000.00
|
|
2
|
Changamwe
|
1.
Jomvu-Mikanjuni Pipeline rehabilitation
works
|
Changamwe
|
2,000,000.00
|
|
2. Bokole-Aldina-Kwapunda W/P
|
Changamwe
|
8,000,000.00
|
|
|
|
3. Extension of West Mainland Sewer line
|
Changamwe
|
5,000,000.00
|
|
3
|
Kisauni
|
1.
Kongowea-Maweni Pipeline extension
|
Kisauni
|
4,000,000.00
|
|
2. Bamburi pipeline extension
|
Kisauni
|
7,000,000.00
|
|
4
|
Mvita
|
1. Tudor
District
Hospital
WP
|
Mvita
|
4,500,000.00
|
|
2.
Rehabilitation
Island Sewerage System
|
Mvita
|
10,000,000.00
|
|
5
|
Tana Delta
|
1.Augumentation
of Garsen water supply
|
Garsen
|
3,000,000.00
|
|
2. Rehabilitation of the Ngao water supply
|
Garsen
|
5,000,000.00
|
|
6
|
Tana River/Galole
|
Rehabilitation
of Hola w/supply
|
Galole
|
4,000,000.00
|
|
7
|
Tana North
|
Rehabilitation
of Madogo water supply
|
Bura
|
4,000,000.00
|
|
8
|
Msambweni
|
Rehabilitation
of Kikoneni water supply
|
Msambweni
|
7,000,000.00
|
|
9
|
Kwale
|
1.
Kibuyuni-Mangawani water project
|
Matuga
|
6,000,000.00
|
|
2. Madabara
-Kwale water supply
|
Matuga
|
8,000,000.00
|
|
10
|
Kinango
|
Dumbule Gandini Water project
|
Kinango
|
8,000,000.00
|
|
11
|
Taita/Wundanyi
|
1. Daku Mbulia Water project
|
Wundanyi
|
7,000,000.00
|
|
2. Sasenyi-Paranga water project
|
|
3. Sasenyi-Kishushe Water project
|
|
12
|
Mwatate
|
Mwasoko Water Project
|
Mwatate
|
6,000,000.00
|
|
13
|
Voi
|
1. Mbololo Water Project
|
Voi
|
6,000,000.00
|
|
2. Voi water supply/Kaloleni
|
Voi
|
6,500,000.00
|
|
3. Voi water supply/Tanzania
|
Voi
|
1,500,000.00
|
|
14
|
Taveta
|
1. Kitobo Water
Project
|
Taveta
|
10,000,000.00
|
|
2. Augmentation
of Taveta Water Supply
|
Taveta
|
8,000,000.00
|
|
15
|
Kaloleni
|
Kamkunji Dam/Mariakani Water Project
|
Kaloleni
|
8,000,000.00
|
|
16
|
Lamu East
|
Procure and
rehabilitate of Pate Island Djabias
|
Lamu East
|
6,000,000.00
|
|
17
|
Lamu West
|
1. Mokowe overhead steel tank.
|
Lamu West
|
5,000,000.00
|
|
2. Sabasaba-Maramande pipeline
|
Lamu West
|
1,000,000.00
|
|
3. Augmentation of Lamu W/s
|
Lamu West
|
8,000,000.00
|
|
18
|
Kilifi
|
Mwele Chasimba
water Project
|
Bahari
|
5,000,000.00
|
|
19
|
Ganze
|
Improvements of Bamba-Ganze line
|
Ganze
|
6,000,000.00
|
|
20
|
Magarini
|
Magarini-Bungale W/P
|
Magarini
|
10,000,000.00
|
|
21
|
Malindi
|
1.
Mkondoni-Katama Water project
|
Malindi
|
8,000,000.00
|
|
2. Jacaranda
Baraka Tende WP(Jimba)
|
Malindi
|
8,000,000.00
|
|
Total
for Districts
|
|
201,000,000.00
|
|